Hi Rod
I have three Align units, but only one in operation and readily accessible at this time.
The Align transformer, which has not been put into operation at this time, has a 3 Amp quick blow fuse. This is as supplied and the fuse rating is stamped on the ends of the fuse.
The operating unit is fitted on a RF31 mill drill with a home built step down transformer unit constructed using a toroidal transformer. With this unit I experimented a little with fuses starting with a 1 Amp quick blow and working up. After blowing a couple of 3 Amp slow blow fuses I stepped up to a 5 Amp quick blow and have had no further issues.
I haven't experimented with the motor speed setting at start up so I do not know how this might affect the inrush current. I suspect the load on the motor as determined by the alignment and smoothness of operation of the drive train and weight of the table and any work piece on it would have the most affect on the inrush current on start up.
Hope this helps
Pero