      I am at the stage of completing the pipework for the top-feed on my GWR 3.5" gauge loco from the two injectors and the tender hand pump. I have made two vertical clacks for the top feed but now realise that I do not have any provision for the feed from the hand pump to the boiler other than the two top feeds. Would the injector feed be compromised if I tee into the injector feed for the hand pump?

      #1881
      Ken Bevan
      Participant
        @kenbevan42381

        combining the pipework plumbing

        #437155
        Chris Gunn
        Participant
          @chrisgunn36534

          Ken, not if you fit non return valves between the hand pump and injector feeds and the clack, so the injector and pump cannot feed back through the other.

          Chris Gunn

          #437297
          Ken Bevan
          Participant
            @kenbevan42381

            Thanks Chris. I rather hoped that might be the case, but not having fitted injectors on previous builds I wasn't sure.

            Regards

            Ken Bevan

          Viewing 4 posts - 1 through 4 (of 4 total)
          • Please log in to reply to this topic. Registering is free and easy using the links on the menu at the top of this page.

          Latest Replies

          Home Forums Locomotives Topics

          Viewing 25 topics - 1 through 25 (of 25 total)
          Viewing 25 topics - 1 through 25 (of 25 total)

          View full reply list.