        Thought I'd share some very pleasing fabrication of a dome/safety valve cover for my 5" gauge Queensland Railways A-10. These are available as aluminium bronze castings but I thought it would be a rewarding exercise to machine and fabricate from solid brass round and phosphor bronze tube, both scrap "donations" to my workshop of ferrous supplies. Below, machining the top from solid brass round section.

        dome blank machining.jpg

        #177552
        andrew winks
        Participant
          @andrewwinks64215

          step 2, rough out the top and fit to PB tube section.

          dome- early.jpg

          #177553
          andrew winks
          Participant
            @andrewwinks64215

            Weld a former/spigot together to form a die to press the PB into shape. Anneal first. Simple press fabrication from angle, etc. 12 tonne bottle jack provides the encouragement..

            flange forming.jpg

            #177554
            andrew winks
            Participant
              @andrewwinks64215

              looking OK, shape is appealing and even.

              flange forming 2.jpg

              #177555
              andrew winks
              Participant
                @andrewwinks64215

                Check fit..

                trial fit.jpg

                #177556
                andrew winks
                Participant
                  @andrewwinks64215

                  Final skim to size

                  dome- final skim.jpg

                  #177557
                  andrew winks
                  Participant
                    @andrewwinks64215

                    Quite pleasing, close to prototype. Producing these parts is most fun one can have standing up!!

                    finished dome 1.jpg

                    #177566
                    Johnboy25
                    Participant
                      @johnboy25

                      Congrats… Nice piece of work. Certainly looks the part.

                      John

                      #177578
                      Jeff Dayman
                      Participant
                        @jeffdayman43397

                        Great job Andrew, well done. Nice to see a good bit of presswork done in the home shop. JD

                        #177597
                        andrew winks
                        Participant
                          @andrewwinks64215

                          Thanks! Used a similar method to produce the petticoat for the stack.

                          The engine is running on air, boiler was completed and hydrostatic tested in 2014 (I have a bunch of pics on the boiler construction that I will post one day soon) and hope to have first steam up before mid year. Bought the castings in '97 so about time I made some solid progress!

                          Andrew

                        Viewing 11 posts - 1 through 11 (of 11 total)
                        • Please log in to reply to this topic. Registering is free and easy using the links on the menu at the top of this page.

                        Latest Replies

                        Home Forums Locomotives Topics

                        Viewing 25 topics - 1 through 25 (of 25 total)
                        Viewing 25 topics - 1 through 25 (of 25 total)

                        View full reply list.